The project ‚Al Bustan South‘ involves expanding the existing 2.88 kilometre-long, six-lane Al-Bustan Street into an eight-lane highway. It comprises the construction of an expressway to the north of Doha with grade separated junctions, four-lanes dual deck to form a 1,946 meter long bridge structure, including 863 m of on/off ramp bridges.
Until the end of 2019 mageba supplied 214 spherical bearings. In addition, 444 m of mageba expansion joints were supplied and installed, comprising 28 units of TENSA®MODULAR between LR2 to LR9 hybrid joints, of up to 720 mm of maximum movement.
Products: | RESTON®SPHERICAL bearings, TENSA®MODULAR expansion joints of types LR2 to LR9 |
Features: | Hybrid expansion joints |
Installed: | 2018–2020 |
City: | Doha |
Structure: | Highway bridge |
Length: | 1,946 m |
Completion: | 2021 |
Owner: | ASHGAL |
Contractor: | HYUNDAI Engineering & Construction |
Engineer: | PARSONS |