Project description

As part of the renovation of the Argentinian highway system in the region of Cordoba, the Provincial Route 34 between Falda del Cañete and Copina is being ugraded totaling in 16 km of new highway.

The project includes the construction of four viaducts with lengths ranging from 120 to 247 m and with the highest viaduct measuring 75 m facilitating the transport in central Argentina and allowing astonishing views of the area as well.

mageba scope

To support this project, mageba supplied eight expansion joints – one for each end of the four viaducts.

All of the installed TENSA-MODULAR expansion joints are 13 m long. Four of the joints are of type LR3 with three individual movement gaps designed for longitudinal movements of more than 220 mm and transverse movements of +/- 50 mm.

The other four joints, designed for longitudinal movements of 150 mm and transverse movements of +/- 50 mm are of type LR2.

In addition, mageba provided supervision for the installation of the joints.

Refsheet-Viaducto-Altas-Cumbres-Concreting-of -TENSA-MODULAR-joint

Concreting of a TENSA-MODULAR LR2 joint under
the supervision of mageba experts

Refsheet-Viaducto-Altas-Cumbres-Installed-TENSA-MODULAR-joint

One of the LR2 joints after installation on site

Key Data

Products:

TENSA-MODULAR LR2 and LR3 expansion joints

Installed:

2019

City:

Cordoba

Type:

Highway viaducts

Main span:

40 m

Lengths:

240 m, 120 m, 247 m and 160 m

Completion:

2019

Contractor:

Chediack – Britos