Headquarters:
mageba sa
Trafostrasse 1
8180 Bulach
Switzerland
Tel: +41-44-872 40 50
Fax:
The Guan Jiang Kou Bridge nearby Linhai, is a super large bridge that spans the Guan River at the boundary of Lianyungang and Yancheng.
The bridge covers a total length of 7’644 m with a main span of 400 m and a combined approach length of 3’610 m. Moreover, the structure is characterised as a double-pylon, double-plane, semi-floating, steel-concrete composite cable-stayed girder bridge with 167.5 m tall H-shaped bridge towers.
The project is of great importance to cement relations between Lianyungang and Yancheng and also promotes regional economic and social development.
In 2015, mageba manufactured four TENSA MODULAR expansion joints of type LR14, each with 14 individual gaps between surface beams and accommodating longitudinal deck movements of up to 1’120 mm.
Furthermore, these joints were also designed to facilitate larger movements for special load cases such as seismic events.
All parts of the joint are elastically pre-stressed making them highly resistant to fatigue.
Products: | TENSA MODULAR expansion joints of type LR14 |
Installed: | 2015 |
City: | Yancheng |
Structure: | Cable-stayed bridge |
Completion: | 2015 |
Length: | 7’644 m |
Owner: | Jiangsu Provincial Transportation Engineering Construction Bureau |
Contractor: | CCCC First Highway Engineering Co., Ltd. |