Refsheet-Macao-Bridge-mainimg

Hong Kong

Macao Bridge – The Hong Kong Link Road

Project description

The Hong Kong Link Road is a 12 km dual 3-lane carriageway bridge, connecting the Hong Kong – Zhuhai – Macao Main Bridge (HZMB) at the Hong Kong Special Administrative Region (HKSAR) boundary with the Hong Kong Boundary Crossing Facilities (HKBCF).

The Hong Kong Link Road comprises a 9.4 km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1 km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6 km long at-grade road section on the reclamation connecting to the HKBCF.

mageba scope

mageba is supplying 208 earthquake bearings RESTON-SPHERICAL for vertical loads of up to 94,700 kN and high horizontal loads at the same time, while allowing large movements. The bearings have a special fuse system that was specially developed for the first ever seismic design requirement in Hong Kong.

mageba also provided 4 expansion joints of type TENSA-MODULAR LR8-LS and 37 TENSA-FINGER expansion joints. Modular expansion joints allow movements and rotations in any direction and assure a smooth driving comfort.

Refsheet-Macao-Bridge-img1

An installed RESTON-SPHERICAL bearing

Visit of a TENSA-FINGER RSFD joint installed on Hongkong-Zhuhai-Macau Bridge

An installed RESTON-SPHERICAL bearing

En bref

Products:

RESTON-SPHERICAL earthquake bearings, TENSA-FINGER expansion joints, TENSA-MODULAR expansion joints LR8-LS

Features:

Earthquake fuse system for bearings at ULS earthquake event

Installed:

2014–2017

City:

Hong Kong

Type:

Long viaduct section

Length:

12 km

Contractor:

Dragages – China Harbour – VSL Joint Venture

Engineer:

Ove Arup & Partners Hong Kong Ltd.

Documents