Refsheet-Peenebrücke-mainimg

Германия

Peene Bridge Wolgast

Project description

The Peene Bridge Wolgast is a combined road and rail bascule bridge over the Peene River in Wolgast. It connects the island of Usedom with Wolgast Castle Island, which is connected to the mainland of Western Pomerania via the “Schlossgraben” Bridge and a railroad bridge.

The Peene Bridge is crossed by the federal road 111 and the railroad line Züssow-Wolgast Hafen with its extension to Świnoujście Centrum.

The leaf of the bridge is 19 m wide and 42 m long. The elevated levers equipped with counterweights control the bridge’s mechanism and are visible from distance due to their height and dimensions. With the leaf open, the bridge’s navigation channel is 30 m wide.

mageba scope

A total of 24 bearings were designed, manufactured, delivered, partially installed and finally approved by mageba (at that time still under the name “Sollinger Hütte”) to support the superstructures on the piers and abutments.

Among the bearings installed are four horizontal force bearings, four longitudinal guide bearings and 16 spherical bearings allowing movement in all directions.

In 2022, a refurbishment project was carried out on the expansion joints.

The existing, worn-out joints were replaced by modern, noise-reducing TENSA-MODULAR lamella as well as TENSA-MAT mat joints supplied by ­mageba.

In the course of this refurbishment, we also replaced the finger plates at the tip of the leaves.

Refsheet-Peenebrücke-installed-mat-joint

New mat expansion joint as installed

Refsheet-Peenebrücke-horizontal-force-bearing

Installed horizontal force bearing

Ключевая информация

Products:

Horizontal force bearings, Guide bearings,Spherical bearings, TENSA-MAT mat joint, TENSA-GRIP RS-LS 100 „ULTRA“ single gap joint

Installed:

1996 / 2022

City:

Wolgast

Structure:

Bascule bridge / Rolling lift bridge

Completion:

1997

Length:

256 m

Owner:

Federal Republic of Germany

Contractor:

Land Mecklenburg-Vorpommern

Architect:

Oskar Lehmann